Post tender estimate
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM2: Detailed measurement for building works, a post tender estimate is:
…a cost estimate carried out after the evaluation of tenders to corroborate the funds required by the employer to complete the building project. |
A post tender estimate should be prepared after tender evaluation and any tender negotiations or tender adjustments have been completed, but before the final decision to invest is made by the client. It includes known construction costs, design team fees, other development/project costs (where these are part of the cost plan) and residual risks.
The purpose of the post-tender estimate is to confirm the amount of funding that will be required in order to complete the project, allowing the client to satisfy themselves that sufficient funding will be available. It may also be used as the control estimate during the construction process.
NB: A pre-tender estimate (PTE) is the final estimate of the likely cost of the works described by the completed tender documents. It provides a final comparison with the budget, and along with the cash flow estimate enables the client to confirm that sufficient funds are available before committing to seeking tenders. For more information see: Pre-tender estimate.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Cash flow projection.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Estimate.
- Initial cost appraisals.
- Investment decision maker.
- NRM2.
- Pre-tender estimate.
- Tender evaluation.
- Tender negotiation.
- Tender pricing document.
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Comments