Post tender estimate
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM2: Detailed measurement for building works, a post tender estimate is:
…a cost estimate carried out after the evaluation of tenders to corroborate the funds required by the employer to complete the building project. |
A post tender estimate should be prepared after tender evaluation and any tender negotiations or tender adjustments have been completed, but before the final decision to invest is made by the client. It includes known construction costs, design team fees, other development/project costs (where these are part of the cost plan) and residual risks.
The purpose of the post-tender estimate is to confirm the amount of funding that will be required in order to complete the project, allowing the client to satisfy themselves that sufficient funding will be available. It may also be used as the control estimate during the construction process.
NB: A pre-tender estimate (PTE) is the final estimate of the likely cost of the works described by the completed tender documents. It provides a final comparison with the budget, and along with the cash flow estimate enables the client to confirm that sufficient funds are available before committing to seeking tenders. For more information see: Pre-tender estimate.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Cash flow projection.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Estimate.
- Initial cost appraisals.
- Investment decision maker.
- NRM2.
- Pre-tender estimate.
- Tender evaluation.
- Tender negotiation.
- Tender pricing document.
Featured articles and news
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Comments